Title: Holy Trinity Church, Twickenham
Date: June 2008

  • Client: Holy Trinity Church
  • Value: 83k
  • Duration: 8 weeks
  • Haymills Team: London Special Works


Haymills New Build

 

Title: Lawrence Court, Huntingdon
Date: May 2008

Client: Clegg Developments
Value: £816,500
Duration: 32 weeks
Haymills Team: Conservation

Haymills New Build

 

Title: 8 High Street, Stamford
Date: April 2008

Client: Malabar Estates Ltd
Value: £205k
Duration: 15 weeks
Haymills Team: Conservation


Haymills New Build

 

Title: Royal Ballet School Phase Three
Date: March 2008

Client: Royal Ballet School
Value: £1.7m
Duration: 48 Weeks
Haymills Team: London Special Works



Haymills New Build

 

Title: British Museum
Date: February 2008

Client: British Museum
Value: £250k
Duration: 32 Weeks
Haymills Team: Special Works


Haymills New Build

 

Title: West Thurrock Primary School, Essex
Date: January 2008

Client: Thurrock Council
Value: £4.7m
Duration: 49 Weeks
Haymills Team: Southern Business Unit

Haymills New Build

 

Title: Department of Plant Sciences, Cambridge
Date: December 2007

 Client: University of Cambridge
 Value: £3m
 Duration: 39 Weeks
 Haymills Team: East Anglian Projects


Haymills New Build

 

Title: Flagship Housing Group, East Anglia
Date: November 2007

Client: Flagship Housing Association
Value: £43m
Duration: Six years
Haymills Team: Property Services

Haymills New Build

 

Title: Wrest Park, Silsoe, Bedfordshire
Date: October 2007

Value: £400k
Client: English Heritage
Duration: 21 Weeks
Haymills Team: Conservation



Haymills New Build

 

Title: Emanuel College, Cambridge
Date: August 2007

  • Value: £1.8m
  • Client: Blue Lion Ltd
  • Duration: 58 weeks
  • Haymills Team: East Anglian Projects


Haymills New Build

 

Title: 31 Dereham High Street, Norfolk
Date: July 2007

  • Value: 250k
  • Client: Private
  • Duration: 14 weeks
  • Haymills Team: Property Services


Haymills New Build

 

Title: Bishops Challoner Catholic Collegiate School, Tower Hamlets
Date: June 2007

  • Value: £12m
  • Client: Archdiocese of Westminster
  • Haymills Team: LONDON Business Unit


Haymills New Build

 

Title: 155 - 171 Tooley Street,
Date: May 2007

  • Value: £5m
  • Client: More London Development Ltd
  • Haymills Team: LONDON Business Unit

 



Haymills New Build

 

Title: Aldeburgh Music
Date: April 2007

  • Value: £5.3m
  • Client: Aldeburgh Music
  • Team: East Anglia Business Unit


Haymills New Build

 

Title: Holloway Road
Date: March 2007

  • Value: £8.5m
  • Client: Shaftesbury House (Development) Ltd
  • Duration: 77 weeks
  • Team: London Business Unit


Haymills New Build

 

Title: Cranfield University, Bedfordshire
Date: February 2007

  • Value: £11m
  • Client: Cranfield University
  • Duration: 65 weeks
  • Haymills Team: East Anglia Projects


Haymills New Build

 

Title: Anglesey Abbey Visitor Centre
Date: February 2007

  • Value: £2.8m
  • Client: The National Trust
  • Duration: 46 weeks
  • Team: East Anglia Projects


Haymills New Build

 

Title: Soule Buildings, RAF Welford
Date: December 2006

  • Value: £1.4m
  • Client: Defence Estates
  • Duration: 42 weeks
  • Team: Property Services


Haymills New Build

 

Title: Treetops School, Grays, Essex
Date: November 2006

  • Value: £10.8m
  • Client: Thurrock Council
  • Duration: 62 weeks
  • Team: Southern Business Unit


Haymills New Build

 

Title: Altitude 25, Croydon
Date: October 2006

  • Value: £31.8m
  • Client: Plumdeah Ltd (Howard Holdings)
  • Duration: 116 weeks
  • Haymills Team: London Business Unit


Haymills New Build

 

Title: Brandon Mausoleum
Date: September 2006

  • Value: £103,000
  • Client: Suffolk County Council
  • Haymills Team: Conservation


Haymills New Build

 

Title: Treehouse National Centre for Autism
Date: September 2006

  • Value: £6m
  • Client: The Treehouse Trust
  • Haymills Team: London Business Unit


Haymills New Build

 

Title: Walden House, Huntingdon
Date: August 2006

  • Value: £965,000
  • Client: Clegg Developments
  • Duration: 60 weeks
  • Haymills Team: Conservation Business Unit


Haymills New Build

 

Title: The Perse School for Girls, Cambridge
Date: July 2006

  • Value: £3.3m
  • Client: The Perse School for Girls
  • Duration: 72 weeks
  • Haymills Team: East Anglian Projects Team


Haymills New Build

 

Title: University of Sussex, Brighton - new residence scheme
Date: June 2006

  • Value: £10m
  • Client: University of Sussex
  • Duration: 56 weeks
  • Haymills Team: Southern Business Unit


Haymills New Build

 

Title: Knebworth House, Knebworth
Date: May 2006

  • Value: £5k
  • Client: Lytton Enterprises Ltd
  • Start: 24 May 2006
  • Haymills Team: Conservation Business Unit


Haymills New Build

 

Title: Telephone Exchange, London SW1
Date: April 2006

  • Value: £8m
  • Client: Cadogan Estates Ltd
  • Duration: 83 weeks
  • Haymills Team: London Business Unit


Haymills New Build

 

Title: St Nicholas School, Canterbury
Date: April 2006

  • Value: £4m
  • Client: Kent County Council
  • Duration: 85 weeks
  • Haymills Team: Southern Business Unit


Haymills New Build

 

Title: Cumberland Terrace, Gibraltar
Date: March 2006

  • Value: £12.9m
  • Client: OEM Cumberland Developments Ltd
  • Duration: 18 months
  • Haymills Team: Special Projects in Gibraltar


Haymills New Build

 

Title: Nelsons View, Gibraltar
Date: February 2006

  • Value: £11.4m
  • Client: OEM Cumberland Developments Ltd
  • Duartion: 18 months
  • Haymills Team: Special Projects in Gibraltar


Haymills New Build

 

Title: The British Museum
Date: January 2006

  • Value: 1.6m
  • Client: The British Museum
  • Duration: 19 week project commencing 23/01/06
  • Haymills Team: London Special Works


Haymills New Build

 

Title: Long Lane Farm, Peterborough
Date: December 2005

  • Value: £136,000
  • Client: Private
  • Duration: 19 weeks commenced 03/01/06


Haymills New Build

 

 

Title: High Street, Dereham, Norfolk
Date: December 2005

  • Value: £190,000
  • Client: Breckland District Council
  • Duration: 20 weeks commenced 05/12/05
  • Haymills Business Unit: Property Services


Haymills New Build

 

 

Title: Court Farm House, Oxfordshire
Date: November 2005

  • Value: £685,000 
  • Client: Private
  • Duration: 34 weeks commenced in November 05
  • Haymills Business Unit: Conservation


Haymills New Build

 

 

Title: Adnams Distribution Warehouse, Suffolk
Date: October 2005

  • Value: £5.8m
  • Client Adnams PLC
  • Duration: 40 weeks commenced 31/10/05
  • Haymills Team: East Anglia Projects


Haymills New Build

 

 

Copyright © Haymills 2006 All Rights Reserved. | website terms and conditions |
add to favourites | site map | links | designed by sms

W3S CSS Compatibility Standard